Photocopy of Site Plan Issued By Building Control Branch in Current Owner’s Name
Photocopy of CNIC of the Owner
Original paid Challan of Drawing Scrutiny Fee
General Undertaking on Affidavit Rs.50/- (Specimen available with Customer Care)
Undertaking on Affidavit Rs.50/- For Temp Lavatory in Residential Buildings (Specimen available with Customer Care)
Undertaking on Affidavit Rs.50/- in case of Basement (Specimen available with Customer Care)
Undertaking on Affidavit Rs.50/- For Swimming Pool for Residential Building. (Specimen available with Customer Care)
No claim of services on Affidavit Rs.50/- for (Ext, DD, XX, Phase – V, VI, VII, VIII & IX)
Note:
All undertakings to be duly signed by owner and attested by the Oath Commissioner.
Procedure
The Building drawing plan documents will be submitted to Customer Care Counter Nos. 6,7,8 & 9 for detailed checking.
Customer Care Counter will issue payment slip for generation of challan by Finance Branch.
The Customer Services Officer will issue payment challan according to the payment slip which will be paid in branches of banks mentioned on reverse of challan.
A photocopy of paid challan will be attached with the Building Drawings / Plans along-with documents tagged in a file.
Acknowledgment Slip will be issued to client for the submission of Building Drawings/Plans.
After receiving the approval letter of drawing, member will visit Building Control Branch and get the Payment Slip for TIP Tax. Thereafter client will get the Payment Challan from Finance Branch for deposit in National Bank of Pakistan (NBP).
Owner will provide 3 x Copies of Paid Challan to Building Control Branch and collect the Building Drawing / Plan.
Note
After approval of Building Drawing / Plan, member will obtain demarcation from DHA Lahore, after which construction should commence within one month and completion of building within two years.
Security Charges & Non utilization fee (If applicable)
Any other charges as intimated by Finance Branch
Client will be informed by Building Control Branch in case of construction violation in house / building.
Client will coordinate with Transfer & Record Branch and Finance Branch for payment of dues and date of transfer.
Documents Required
Copy of Site Plan issued by Building Control Branch in name of present owner.
Copy of Completion Certificate (in case of house / building).
Copy of Allotment / Transfer Letter.
Copy of Computerized National Identity Card of owner.
No Objection Certificate from Cantt Board (relating to TIP Tax).
No Objection Certificate from W&R Directorate, GHQ Rawalpindi in case of service benefit plots / plots allotted out of defence quota from GHQ AG’s Branch.
Procedure
Client will submit No Demand Certificate Form along-with required documents to Customer Services Officer (Transfer & Record Branch).
DHA field staff will visit the site in case of constructed house/building for ground verification.
If construction violations are observed, owner will be informed on corresponding address or in case of no violation No Demand Certificate will be processed to Transfer & Records Branch through Finance Branch for clearance of dues and transfer of plot.
The client can check the status and collect the Payment Challan from Finance Branch, DHA office.
Demarcation of the plot is required before construction. This procedure takes place after the approval of Building Plans.
Service
Timeline
Charges
Delivery
Demarcation
5 working days
8 working days (Phase 8)
Nil
Building Control Branch
Documents Required
NOC for dues clearance from Finance.
Demarcation and Pass Performa to be filled by the owner or DHA’s special power of attorney holder.
Photocopy of TIP tax for phase I to V and VIII, and photocopy of IPF for phase VI-VII.
Undertaking of “Own Water Supply Arrangements” on Stamp paper of Rs.50/- duly attested by Oath Commissioner.
Undertaking of “Stacking of Material and Temporary Hut” on Stamp Paper of worth Rs.50/- duly attested by Oath Commissioner.
Photocopy of ‘Drawing approval Letter’ issued by DHA.
Note:
Demarcation is valid for one month only in case construction activity has not commenced.
After receiving the demarcation papers, Owner / DHA’s Special Power of Attorney Holder is bound to construct Septic Tank & Temporary Lavatory as per approved drawing within the plot area and both should be ready before the field staff visit.
Procedure
Demarcation Forms are available at Customer Care Services, DHA Office.
Complete set of documents and Demarcation Forms duly signed will be submitted to Customer Services Officer Building Control Branch.
Client will be given an acknowledgment and date to obtain Demarcation Papers.
Note:
Demarcation is valid for one month only in case construction activity has not commenced.
An application from owner to Director Building Control requesting for the opening of temporary sewerage connection.
Procedure
Client can start the construction work after receiving demarcation papers and is bound to construct Septic Tank as per approved drawing and Temporary Lavatory within the plot area.
The application for Temporary Sewerage Connection will be submitted to Customer Services Officer (Building Control Branch).
Septic Tank & Temporary Lavatory (connected with each other) should be ready before the field staff visit within 10-12 working days.
Temporary Sewerage Connection will be provided to particular house / building when Temporary Lavatory has been constructed and connected with Septic Tank.
Subject to finishing of construction activities without construction violations
Water Connection Fee @ Rs. 10,000/-
Sewerage Connection Fee @ Rs.5000/-
Water and Sewerage connections will be provided through main pipes on site
Documents Required
Application form duly filled by the Owner / Attorney.
Original and 1 x photocopy of paid challan of Water & Sewerage Connection charges.
Photocopy of CNIC of the Owner / Attorney.
2 x identical colored photographs of front elevation of house / building on photo paper (6” x 4” Size) showing complete elevation including beam area / driveway and paved area etc. In case of corner plot, 2 x additional photograph (6” x 4” Size) of side elevation are also required.
1 x Photocopy of Site Plan with current Owner’s name.
Note:
After site visit by the field staff of building control branch and if satisfied with the construction as per approved drawing, having no construction violations, recommendation for opening of both the connections is made.
Water & Sewerage Connection will be provided after flooring, plastering, gate, doors, windows, electrification and plumbing of the house / building are ready.
Procedure
Water & Sewerage Connection Forms are available at the Reception of Customer Care Services DHA Office free of cost .
After collecting the Water & Sewerage Form client has to visit Customer Services Officer (Building Control Branch) for the preparation of Water & Sewerage Connection Charges.
The client will pay the dues as per Payment Challan in the designated bank.
Acknowledgment will be issued by Customer Care Services (Representative Building Control Branch).
Water & Sewerage Connections will be provided after flooring, plastering, gate, doors, windows, electrification and plumbing of the house / building are ready.
After site visit by the field staff of Building Control Branch and if satisfied with the construction as per approved drawing, having no construction violations, recommendation for opening of both the connections is made.
After provision of Water Connection, previously installed water pump by the owner for construction activities will be removed according to DHA Construction Bye-laws.
Sewerage Connection will be completely opened for the proper out flow after completion of above.
Completion Certificate will be delivered to the applicant’s address.
Documents Required
Application addressed to Director Building Control, requesting for the issuance of Completion Certificate.
2 x identical colored photographs of front elevation of house / building on photo paper (6″ x 4″ Size) showing complete elevation including berm area / driveway and paved area etc. In case of corner plot, 2 x additional photographs (6″ x 4″ Size) of side elevation are also required.
2 x Set of approved drawing (Ammonia Prints).
Original paid challan on account of Completion Certificate Fee.
Photocopy of paid challan on account of “Late Completion Charges” if paid earlier.
Photocopy of paid challan of Water & Sewerage Connection.
Photocopy of DHA Letter regarding Sewerage Opening (Last paid bill of Water & Sewerage in case of Ex. Air Avenue Ph – VIII).
Photocopy of paid challan on account of “Sewer Tempering Charges”.
Photocopy of CNIC of the Owner / DHA Special Power of Attorney Holder.
Procedure
Submit the application along with the required documents to the Customer Services Officer (Building Control Branch Representative).
An acknowledgment will be given after the submission of the documents.
All the members who have made changes / deviations from the approved Building Drawings / Plans should submit the revised Building Drawings / Plans to regularize the construction before applying for the Completion Certificate.
On receipt of application for the Completion Certificate DHA field staff will inspect the House / Building. If it is as per approved building Drawing / Plan and has no construction violation, then Completion Certificate will be issued or observations will be communicated through Building Control Branch.
No Transfer of House / Building will be processed even on HIBA without obtaining Completion Certificate.
Permission letter will be dispatched at applicant’s address.
Documents Required
Application from Owner / Attorney to Director Building Control.
Copy of Computerized National Identity Card of Owner.
Copy of Completion Certificate of particular house / building.
Procedure
The required documents will be submitted to the Customer Care Services.
DHA field staff will visit the site.
A letter will be dispatched along-with payment challan on account of Security Charges and specimen of undertaking for demolition of house / building to the Director Building Control.
Copy of paid challan and undertaking on Rs. 50/- Stamp Paper will be submitted at the Customer Services Centre.
Permission letter for Demolition of House/Building will be dispatched to the owner after verification of documents and inspection of house / building at site.
Permission letter will be dispatched to the customer’s address.
Documents Required
Application from Owner to Director Building Control.
Copy of Computerized National Identity Card of Owner.
Procedure
The required documents will be submitted to the Customer Care Services.
DHA field staff will visit the site.
A letter will be dispatched to the applicant along with payment challan on account of security charges and specimen of undertaking for use of mechanical excavator.
Copy of paid challan and undertaking on Rs 50/- Stamp Paper will be submitted at the Customer Care Services.
Permission letter for use of excavator will be dispatched to the Owner’s address.
NOTE: Excavation with excavator without permission will be charged for Rs. 50,000
Use of open plot for stacking of construction material
08 Working Days
Free of cost
Permission letter will be dispatched at applicant’s address.
Documents Required
Application from Owner / Attorney.
Copy of Computerized National Identity Card of Owner.
Procedure
The required documents should be submitted at the Customer Care Services.
DHA field staff will visit the site.
A letter will be dispatched to the applicant along-with specimen of undertaking for use of open plot for stacking of construction material and construction of temporary hut.
Undertaking on Rs. 50/- Stamp Paper will be submitted at Customer Care Services by the applicant.
Permission letter for use of open plot will be sent to the Owner / Attorney.
Reference – Source and Credit: https://dhalahore.org/